Log in

USACE NAV/OPS Report

Tuesday, March 24, 2020 5:11 PM | Anonymous

USACE NAV/OPS Report

24 March 2020

CHARLESTON HARBOR POST 45:

-Entrance Channel Contract 1:  GLDD hopper dredging to resume next hopper season.

-Entrance Channel Contract 2:  Hopper dredge ELLIS ISLAND has departed for the season.  Hopper dredge TERRAPIN ISLAND mobilized the week of 10 MAR 20 and is dredging new work material in AS 6 and 7.

-Lower Harbor Contract to Wando Welch Terminal (WWT):  Norfolk Dredging bucket dredges Atlantic and Virginian dredging new work material in Wando River reaches.

-Lower Harbor Contract to Hugh Leatherman Terminal (HLT):  Plans & Specs being finalized.  Anticipate solicitation by the mid May 2020.

-Upper Harbor Contract:  Plans & Specs expected to be finalized by mid April 2020.  Anticipate solicitation by the mid June 2020.

CHARLESTON HARBOR O&M:

-FY19 CHARLESTON HARBOR UPPEER REACHES O&M:  Southern Dredging has returned.  Shoal 4 Navy Yard Reach complete.  Shoal 3 Daniel Island Bend AD survey conducted.

AIWW:

-FY18 AIWW CRITICAL SHOAL DREDGING WINYAH BAY TO CHARLESTON:  Goodloe completed Shoal 6 Matthews Cut before being released to Wilmington.  Anticipate return of dredges in mid-April 2020 to complete the project.   

.


CONNECT WITH US


Call: 
843-577-7678
 
Email:
staff@maritimesc.org

  
Mail:  
 4500 Leeds Ave, Suite 207
   N. Charleston, SC  29405

   
    Visit:
     4500 Leeds Ave, Suite 207
   N. Charleston, SC  29405

Powered by Wild Apricot Membership Software