Army Corps of Engineers NAV/OPS update

Thursday, July 23, 2020 2:19 PM | Nick Wong (Administrator)

USACE NAV/OPS Report

23 July 2020

CHARLESTON HARBOR POST 45:

-Entrance Channel Contract 1:  GLDD hopper dredging to resume next hopper season.

-Entrance Channel Contract 2: GLDD Cutter Suction dredge TEXAS has finished dredging in AS 1.  TEXAS moved to AS 6 to join Cutter Suction dredge CAROLINE to complete dredging in AS 6, then both dredges will move to AS7. 

-Lower Harbor Contract to Wando Welch Terminal (WWT):  Norfolk Dredging dredges ATLANTIC and VIRGINIAN continue dredging New Work material in AS 6, Lower Wando Reach and AS 8 Wando River Turning Basin.  

-Lower Harbor Contract to Hugh Leatherman Terminal (HLT):  Contract advertised 07 JUL 20.  Award scheduled 28 AUG 20

-Upper Harbor Contract:  Contract solicitation scheduled for 30 JUL 20.  Award scheduled 25 SEP 20.

CHARLESTON HARBOR O&M:

-FY19 CHARLESTON HARBOR UPPEER REACHES O&M:  Dredging complete.

JBC:

- FY20 JOINT BASE CHARLESTON DREDGING:  Contract solicitation scheduled for 24 JUL 20.  Award scheduled 14 SEP 20.

AIWW:

-FY18 AIWW CRITICAL SHOAL DREDGING WINYAH BAY TO CHARLESTON:  Goodloe continues dredging in Shoal 7 Jeremy Creek.


From Scott Glass

CONNECT WITH US


Call: 
843-577-7678
 
Email:
staff@maritimesc.org

  
Mail:  
 4500 Leeds Ave, Suite 229 W
   N. Charleston, SC  29405

   
    Visit:
     4500 Leeds Ave, Suite 229 W
   N. Charleston, SC  29405

Powered by Wild Apricot Membership Software